New sports bar takes shape

Close on the heels of completion of the new balcony, the works on the ground floor bar and office are proceeding apace.

The office / reception is almost completed and will be ready for occupation within ten days and the extended club room will have decorations completed shortly, air conditioning installed, flooring laid next week with the new bar being installed the following week.

IMG_4316 edited.jpgIMG_4310 edited.jpgIMG_4309 edited.jpg

 

We are currently sorting out furniture for the new bar and have received offers of help with this for which we are extremely grateful.

 

Still looking for a few generous members to put up the remaining £3K needed to install a 'state of the art' TV projector and drop down screen to complete what will be a very exciting new facility for our members and guests. (If you would like to help out with this please contact Lionel or Steve)